. Here is the timeline for the project:
- Sept. 14th - Wireframes start
- Sept. 21st - Wireframes demo + feedback
- Sept. 25th - 8th - Quietly to start copy development
- Sept. 28th - Wireframes revisions + sign-off
- Oct. 1st - Design mockups start
- Oct. 5th - Design demo
- Oct. 12th - Design revisions + sign-off
- Oct. 15th - Front-end + WP dev start <Quietly copy - final>
- Oct. 26th - Website demo + feedback
- Nov. 1st - Launch
Thanks,
Morgan
Further to discussions with
- Sept. 14th - Wireframes start
- Sept. 21st - Wireframes demo + feedback
- Sept. 25th - 8th - Quietly to start copy development
- Sept. 28th - Wireframes revisions + sign-off
- Oct. 1st - Design mockups start
- Oct. 5th - Design demo
- Oct. 12th - Design revisions + sign-off
- Oct. 15th - Front-end + WP dev start <Quietly copy - final>
- Oct. 26th - Website demo + feedback
- Nov. 1st - Launch