TOLOGIX - Infrastructure LawGuide (ILG)

Make Date of Concession Agreement a non-required field

Assigned to
Hiren Patel Hiren P. Jitesh Dhuravala, DevIT Jitesh D.
Notes
Further to the video below, there are projects where no data will be available for the Date Of Concession Agreement (MM/DD/YYYY) * field. Two options are available to fix the problem:
  1. Make field a non-required field
  2. Make field a non-hardcoded field that is available in managed fields, and then the admin user will be able to remove the required field option with the meta field management page.
The second option is preferred, but the first option is fine if there are technical reason for keeping the field a hardcoded field.


Comments & Events

Hiren Patel
Hi Morgan Maguire, CEO Morgan ,

as per your suggestion we have to choose 2 option for "Date Of Concession Agreement (MM/DD/YYYY) "  and convert this  field to non-hardcoded field.

Please check and let us know.

Thanks

Hiren

cc: Ketan Sondarva, Technical Project Manager at DevIT Ketan  
Morgan Maguire, CEO
OK. Great Hiren Patel Hiren . Please implement option 2. Note when the field is converted into a managed field, please move the field in between Financial Close and Concession Period:



Thanks,

Morgan
Hiren Patel
Hi Morgan Maguire, CEO Morgan ,

This has been done.Please check and let us know.

Thanks,

Hiren

cc: Ketan Sondarva, Technical Project Manager at DevIT Ketan Jitesh Dhuravala, DevIT Jitesh  
Morgan Maguire, CEO
Looks good Hiren Patel Hiren . Marking to-do complete.

Thanks,

Morgan 
Morgan Maguire, CEO
Morgan Maguire completed this to-do.