TOLOGIX - ISLG App Rebuild

Document 2021-03-25 08.19.13 Weekly Tologix-DevIT-Industrial Meeting 81175607260.mp4 (239 MB)

Download ↓

Hello all,

Here is the recording from today's meeting, and the action items:
  • Jitesh Dhuravala, DevIT Jitesh please confirm with Irit Weinfeld Irit when all batch 2 documents are uploaded to app.islg, and please updated the "Uploaded to ISLG" columns as documents are added to the system
    • When batch 2 is complete, immediately start uploading all batch 3 documents. We need to get all completed documents on app.islg as soon as possible.
  • Harsh Parikh, Tech Lead at DevIT Harsh and Ketan Sondarva, Technical Project Manager at DevIT Ketan , please provide update tomorrow after investigation resolution to ISLG Reports problem: Problem with Reports - TOLOGIX - ISLG App Rebuild. As discussed we need to resolve the issues with only displaying the values that are applicable to the record value for all child fields without compromising the performance of generating reports in ISLG Reports.
  • Harsh Parikh, Tech Lead at DevIT Harsh , please confirm when final fixes to FTS and DD search are deployed on staging.islg and Naomi Joanis, UX Team Lead at Industrial Naomi and Morgan Maguire, CEO Morgan  will perform final testing before final deployment to app.islg.
  • Harsh Parikh, Tech Lead at DevIT Harsh please implement changes to session tracking regarding the closing of browser tabs based on what you've outlined here: https://industrialagency.tpondemand.com/RestUI/Board.aspx#page=board/5361190942734992086&appConfig=eyJhY2lkIjoiOTk1NDg2NkUwM0I1RTJGMzQ5NjgyOTdFRjk2NkRGN0YifQ==&searchPopup=userstory/22797
    • Naomi Joanis, UX Team Lead at Industrial Naomi when implemented, please ensure testing is performed to ensure 30 minutes timeout activates on all major browsers (Chrome, Safari, Firefox and Edge).
  • Naomi Joanis, UX Team Lead at Industrial Naomi , please ensure any user stories/bugs that are in UAT are review tomorrow the following users stories are resolved to the last deployment to app.islg this weekend:
    • ISLG Admin
      • 22551 | Bug | [Staging] Individual org report > dispute reference field > missing org fields
      • 22554 | Bug | [Staging] Comparative Person Report > Custom column > No data
      • 22557 | Bug | [Staging] Comparative Org Report > Organization names with commas changes order of words
      • 22581 | Bug | [Staging] Individual Organization Report > Not able to add org reference fields
      • 22582 | Bug | [Staging] Not able to add organization to dispute record
    • ISLG Subscriber
      • 22577 Bug [Staging] Reports > Positioning of values in reports is off
      • 22579 Bug [Staging] Reports > By default are not shown alphabetically
      • 22588 Bug [Staging] Show full integer, symbol and decimal points in report values
      • 22843 UserStory [ISLG Team Feedback] Change Text in Custom Reports Section
      • 22214 Bug [Staging] Optional ST > Popup appears multiple times after I press skip
      • 22653 Bug Password Expiry Emails > Email received twice/daily
      • 22797 UserStory [ISLG Team Feedback] Session Tracking Message On Tab Close
  • Melissa Cowell, General Manager at Industrial Melissa and Naomi Joanis, UX Team Lead at Industrial Naomi , please confirm that issues with Followed Topics outlined here: Notifications within Followed Topics when changes made to Dispute form - TOLOGIX - ISLG App Rebuild are bugs or deficiencies in requirements that we'll resolve post-launch.
  • Morgan Maguire, CEO Morgan will provide Carbon60 with redirect instructions outlined here: Re: Page Redirects List - TOLOGIX - ISLG App Rebuild
    • Redirects will be scheduled for Tuesday, April 6th at 7:00am Vancouver time.
      • This is when the new application goes live.

Comments & Events

Morgan M. posted this on · Download ↓
Ketan Sondarva, Technical Project Manager at DevIT
HI Naomi Joanis, UX Team Lead at Industrial Naomi , Melissa Cowell, General Manager at Industrial Melissa , Morgan Maguire, CEO Morgan  

Meantime, would you please check all items in UAT right now in Target Process and update us by end of today so if still any issue we can resolve by this week only.

Thanks,
Ketan Sondarva
Ketan Sondarva, Technical Project Manager at DevIT
Hi Morgan Maguire, CEO Morgan ,

If you can please request to Carbon60 regarding install SSl certificate in both app.islg and staging.islg early next week so that we can verify in both applications running smooth without any issues or we can fix it by next week week only if any.

Thanks,
Ketan Sondarva
Morgan Maguire, CEO
Hi Ketan,

The SSL certificates have already been installed. The only issue outstanding is setting up the redirects from the http pages to the https pages. I've submitted this request, I expect them to perform the tasks today or tomorrow.

Thanks,

Morgan
Naomi Joanis, UX Team Lead at Industrial
Hi Morgan Maguire, CEO Morgan and Ketan Sondarva, Technical Project Manager at DevIT Ketan

Following up on the stories in UAT:
  • ISLG Admin
    • 22551 | Bug | [Staging] Individual org report > dispute reference field > missing org fields
    • 22554 | Bug | [Staging] Comparative Person Report > Custom column > No data
    • 22557 | Bug | [Staging] Comparative Org Report > Organization names with commas changes order of words
    • 22581 | Bug | [Staging] Individual Organization Report > Not able to add org reference fields
    • 22582 | Bug | [Staging] Not able to add organization to dispute record
  • ISLG Subscriber
    • 22577 Bug [Staging] Reports > Positioning of values in reports is off
    • 22579 Bug [Staging] Reports > By default are not shown alphabetically
    • 22588 Bug [Staging] Show full integer, symbol and decimal points in report values
    • 22843 UserStory [ISLG Team Feedback] Change Text in Custom Reports Section (This is not in UAT)
    • 22214 Bug [Staging] Optional ST > Popup appears multiple times after I press skip
    • 22653 Bug Password Expiry Emails > Email received twice/daily
    • 22797 UserStory [ISLG Team Feedback] Session Tracking Message On Tab Close (One issue remaining with this
The ones that are crossed out have been moved to done, and there are notes on the items that aren't crossed out. There is still a remaining issue with FTS as well that Harsh Parikh, Tech Lead at DevIT Harsh and I are discussing through the targetprocess bug (https://industrialagency.tpondemand.com/entity/22502)
Morgan Maguire, CEO
Great. Thanks Naomi Joanis, UX Team Lead at Industrial Naomi .

Currently the following pre-launch items are outstanding:
Ketan Sondarva, Technical Project Manager at DevIT Ketan and Harsh Parikh, Tech Lead at DevIT Harsh , please review the list above and let us know if there any concerns about getting items complete within the deployment schedule, which I understand to be the following (applicable user stories/bugs and to-do's are highlighted):
  • Monday, March 29th: all user stories/bugs and to-do's will be competed on staging.investorstatelawguide.com and pushed to app.investorstatelawguide.
  • Wednesday, March 31st: user data migration scripts will be run and existing users will be synced between legacy and new application.
  • Tuesday, April 6th: users created on legacy app since March 31st will be migrated to new application and redirects (and other applicable changes) will be implemented by Carbon60 at 7:00am to make the ISLG application live.
Thanks,

Morgan
 
Jitesh Dhuravala, DevIT
Hi Irit Weinfeld Irit and Morgan Maguire, CEO Morgan ,

We have uploaded all documents of Batch 2 and Batch 3. Also I have updated respective date into the column " Upload to ISLG". Please check it and confirm.

Thanks,
Jitesh
Morgan Maguire, CEO
Great. Thanks Jitesh Dhuravala, DevIT Jitesh ​.

Irit Weinfeld Irit ​, can you confirm everything is up on the system as expected.

Thanks,

Morgan
Morgan Maguire, CEO
Following-up on above, the following user stories/bugs are now outstanding:

For the remaining user stories/bugs and basecamp to-do's highlighted in yellow, further work is required to resolve issues in the FTS and Followed Topics features. Ketan Sondarva, Technical Project Manager at DevIT Ketan and Harsh Parikh, Tech Lead at DevIT Harsh , will these be resolved before we perform the final push from staging.islg to app.islg tomorrow? Note we need to perform the push as soon as possible, so that Paul Moon Paul and the team have the latest version of the application to complete their work this week.

Thanks,

Morgan
Irit Weinfeld
Hi Morgan Maguire, CEO Morgan and Jitesh Dhuravala, DevIT Jitesh ,

I have spot checked the Automated and Manual HTMLs - and everything I checked is now tracked in the spreadsheets. Thank you.

I have updated the spreadsheets and assigned "Batch 4" for upload.  I have updated the following Basecamp thread: Batch HTML uploading to app.islg

Thank you,
Irit
Morgan Maguire, CEO
Great. Thanks Irit Weinfeld Irit ​.

Morgan
Irit Weinfeld
Hi Morgan Maguire, CEO Morgan ,

I spoke too soon.  This issue has not been resolved.  For example, Dispute Document IC/0422/02, SC/0015/89, SC/0015/86 and IC/0310/02 should not be time stamped on the spreadsheets.  The HTMLs have not been uploaded.  I posted this issue here as well: Batch HTML uploading to app.islg - TOLOGIX - PDF to HTML Conversion

Jitesh Dhuravala, DevIT Jitesh is there a way to filter app.islg Admin site database to show the Dispute Documents that have PDF files but no HTML files uploaded? 

Thank you,
Irit
 
Ketan Sondarva, Technical Project Manager at DevIT
HI Morgan Maguire, CEO Morgan ,

Below highlighted are the updates from our side for pending in ISLG rebuild.

Thanks,
Ketan
Harsh Parikh, Tech Lead at DevIT
Hi Morgan Maguire, CEO Morgan ,

We will integrate dtSearch Indexing on app.islg once FTS Target Process bug will be completed. 

We hope that those bug will be resolved by tomorrow end of day.
Morgan Maguire, CEO
OK. Sounds good. Thanks Harsh Parikh, Tech Lead at DevIT Harsh .

Morgan