August Release
Hi Melisa and Naomi,
Next week, we will release new versions on rebuilddemo.islg. Due to Admin Side changes and Document View module, we need to clear all the test data.
The August release date i have mentioned against appropriate stories in timeline sheet.(https://docs.google.com/spreadsheets/d/1ArmqOfOLDeME0i1OzrnyueIDa6_Xam4P_nZ1ddv5dW8/edit#gid=1264220918)
Next week, we will release new versions on rebuilddemo.islg. Due to Admin Side changes and Document View module, we need to clear all the test data.
The August release date i have mentioned against appropriate stories in timeline sheet.(https://docs.google.com/spreadsheets/d/1ArmqOfOLDeME0i1OzrnyueIDa6_Xam4P_nZ1ddv5dW8/edit#gid=1264220918)
We have resolved bugs of notification module. But some bugs, we are not able to produce.
I would request you to in next release when you test the notification bug then start the video capturing while you perform the testing.
Because, in some cases we need scenario that how you perform that test case.
I'll be sure to record a video for any bugs logged to help recreate them on your end.
Thanks,
Naomi
As, we need to create same scenario if any thing still be there.
As you mentioned here: Re: Certain disputes not expanding Legal Analytics: Costs - PRIORITY - TOLOGIX - ISLG App Rebuild in reply to
I ask, because I'm wondering when we will starting syncing content and features between rebulddemo.islg and rebuild.islg to ensure content is available on rebulddemo.islg for UAT and needed feature updates are available on rebuild.islg. Of course, we would need to take into consideration that live content is being added on rebuild.islg via Legal Analytics, and any syncing between environments would need to protect and preserve data on rebuild.islg.
Thanks,
Morgan
We are maintaining rebuild.islg content. we can not do anything with rebuild.islg content.
If there is any admin side changes then will deploy the changes on both rebuild.islg and rebuilddemo.islg.
But, For Subscriber side changes, we are deploying only on rebuilddemo.islg.
Tomorrow Morning, we are going to deploy the 31 August stories on rebuilddemo.islg. Please take note that we will remove all testing data.
Also, We will deploy Admin high priority changes on rebuild.islg as well.
Let us know when the deployment is complete.
Morgan
I want to flag that there were a couple of user stories that were supposed to be include this morning's release (31-Aug-20) that were not moved to UAT:
Also,
Thanks,
Morgan
In ISLG Admin side, That card is in development and we are working on it and will release with next release date. I update the date in sheet
In ISLG Subscriber, card no. 10112 will move in UAT but card no. 7655 is blocked due to need confirmation from industrial team.
The ISLG Admin card no. 16799 is completed and will move this story in UAT by end of day.
Following status update for ILG.
ILG Admin :
16761 Automated emails > Styles are incorrect
16758 Move Tag > Tag Location field behaviour incorrect
Above two story html template request to Industrial team, both feedback done from our side only pending to change html template in order to make it done.
8990 | Groups > Expiry Date
Above group expiry date also done and we move to UAT with subscriber site publish on tomorrow 3rd September.
ILG Subscriber :
15449 | ILG Team Feedback > [Improvement] Include tag meta-field value details
Above feedback also done, we are uploading tomorrow subscriber site and update in spreadsheet.
Thanks,
Jitesh
Further to comments above by
Thanks,
Morgan
Please let us know once you completed your testing on ISLG. so we can start look into the bugs which you produced.
My understanding is that Industrial is dedicating everyone to UAT right now, and that they are getting through all the user stories released last week as soon as possible. In the meantime, I suggest reviewing and resolving bugs as they are reported. For example, I've identifies 14 user stories in ISLG Subscriber that have been sent back for further development from the August release:
Thanks,
Morgan
That is correct! We are down to 65 user stories and are devoting the majority of the next two days to clearing out the remainder to meet our deadline.
Savannah
Morgan