When I click on the text cross reference from Subject Navigator on the rebuild live site, I am not taken to the specific provision within an instrument as the legacy live site does but to the instrument in general.
This issue is resolved on both rebuild.islg and staging.islg.
Notified 5 people
Paul Moon
Hi
Harsh
:
The issue has not been resolved.
1. The text cross-reference still takes me to the top of the HTML, not specific provision (e.g., Article 46 ICSID Convention) on both rebuild and staging.
2. Loadint time: once I click on the cross-reference, rebuild.islg took about 85 seconds to take me to the top of the ICSID Convention HTML, and staging.islg took about 60 seconds to take me to the top of the ICSID Convention HTML.
In addition to
Paul
's comment above, I noticed that the presentation of the HTML document (which was converted from the XML version available legacy application) lacks a lot of the properties previously available in the legacy application (e.g., Proper Title and TOC), and I am wondering if this has anything to do with why these cross references are not working.
I'm going to post these issues a separate to-do, but I wanted to raise it here in case it assist in understanding the problem.
This issue is resolved on both rebuild.islg and staging.islg.
The issue has not been resolved.
1. The text cross-reference still takes me to the top of the HTML, not specific provision (e.g., Article 46 ICSID Convention) on both rebuild and staging.
2. Loadint time: once I click on the cross-reference, rebuild.islg took about 85 seconds to take me to the top of the ICSID Convention HTML, and staging.islg took about 60 seconds to take me to the top of the ICSID Convention HTML.
I'm going to post these issues a separate to-do, but I wanted to raise it here in case it assist in understanding the problem.
In this task, We will resolve the loading time issue but the TOC rendering will take after post launch.
Hope this is fine.
Yes, we'll resolve the TOC issues with the Treaties and Arbitration Rules post-launch.
Thanks,
Morgan
The Loading time issue is resolved on staging.islg. The TOC issue will see after post launch.
The loading time issue has been resolved, thanks.
Paul